Author: Frankenbach

28 Jun Customer Information 06/19

Dear customers,

we would like to inform you regarding the following current issues:

 

  • Bunker Adjustment Factor for Barge transports in July 2019
  • Update current congestion situation in Rotterdam and Antwerp
  • Thank you for your visit in Munich

 

Bunker Adjustment Factor for Barge Transport in July 2019

The gasoil-price-index monitored by CBRB, Rotterdam, has been stable.
Hence, Bunker Adjustment Factor (BAF) for July 2019 is settled to scale 21 of the Frankenbach BAF Scheme. Kindly take note.

You may find the complete Frankenbach BAF Scheme in the download area of our homepage www.frankenbach.com

 

Update current congestion situation in Rotterdam and Antwerp

We herewith would like to keep you updated about the current handling times in Rotterdam and Antwerp. The waiting times in Rotterdam are up to 24 hours.
The waiting times in Antwerp are up to 20 hours at the moment.

Hence, we would like to point out again that we can neither guarantee arrival times, nor closings and therefore decline any liability (like demurrage and detention).

 

Thank you for your visit in Munich!

We gratefully want to thank all our customers, business partners and of course all newly interested visitors for their attendance at our booth.
As taken place in the last several years, the talks were characterized by high quality and great interest in our transport solutions.

The dialogue partners of all parts of the company are gladly looking forward to further discussions.

 

Frankenbach Container Service GmbH

04 Jun

Dear customers,

we would like to inform you regarding the following current issues:

 

  • Bunker Adjustment Factor for Barge transports in June 2019
  • Terminal Opening Hours during the upcoming holidays
  • Update current congestion situation in Rotterdam and Antwerp
  • Trade Fair ‘transport logistic’ 2019 in Munich from 04th – 7th June 2019

 

Bunker Adjustment Factor for Barge Transport in June 2019

The gasoil-price-index monitored by CBRB, Rotterdam, has risen slightly.
Hence, Bunker Adjustment Factor (BAF) for June 2019 is settled to scale 21 of the Frankenbach BAF Scheme. Kindly take note.

You may find the complete Frankenbach BAF Scheme in the download area of our homepage www.frankenbach.com

 

Terminal Opening Hours during the upcoming holidays

Please consider the upcoming holidays (10.06. and 20.06.) and the resulting shortened working weeks (calendar week 24 and 25) for your transport planning. The FCT container terminal and the office in Mainz will be closed at these times.

Furthermore, there will be limited arrivals and exits in our transport connections in this period of time.

Please kindly consider these restrictions in your transport planning. We therefore ask for early reservations.
Please contact our customer service team in case of any further questions.

Update current congestion situation in Rotterdam and Antwerp

We herewith would like to keep you updated about the current handling times in Rotterdam and Antwerp. The waiting times in Rotterdam are up to 36 hours.
The waiting times in Antwerp are up to 24 hours at the moment.

Hence, we would like to point out again that we can neither guarantee arrival times, nor closings and therefore decline any liability (like demurrage and detention).

 

Trade Fair ‘transport logistic’ 2019 in Munich from 04th – 7th June 2019

The world’s leading trade fair for transport and logistics takes place in Munich from 04th until 7th June 2019.

Frankenbach is on site, you will find us again at Hall B6 at Booth 303/404. Our staff will be available for the business professionals and experts visiting us.

If you are interested in a personal meeting, please feel free to contact us in advance.

We are looking forward to your visit.

You can find further information on the official homepage of the trade fair www.transportlogistic.de.

 

 

Frankenbach Container Service GmbH

31 Oct Customer Information

Dear customers, Today we would like to provide you with the following up-to-date information:

 

• Update Low Water Situation on the Rhine – 31.10.2018

 

We herewith would like to inform you about the already low-lasting low water situation (Kaub showed a water level of 64 cm) on the river Rhine.

By implementing an alternative transport concept we accomplished a reliable and efficient transport on behalf of our customers.

Due to a slightly risen water situation at Kaub, we have to ask you as of 01.11.2018 for shorter closing times up to 12 days after the actual trucking date.

(e.g. trucking date 05.11 – closing seaport earliest 17.11.)

Please kindly take note that KWZ scale 5 of Frankenbach Low Water scale has become applicable.

Due to that situation we have to inform you again that under a gauge level of 81 cm at Kaub we no longer have an obligation of transport and therefore decline any liability (like demurrage and detention).

For questions and further information please feel free to contact our teams customer service and planning.

 

Frankenbach Container Service GmbH

15 Feb Special Announcement

Dear Madam/Sirs

 

due bad weather ( snow and ice ) we partially have to stop work on the terminal, also drivers well be delayed at all positionings today
due that issue.

we will inform you separately for all positionings which will be delayed

 

Frankenbach Container Service

26 Jan Customer Information / Special Announcement

Special message regarding the High Water Marks

Dear ladies and gentlemen,

due to the rising water level, the barge shipping between Coblenz and Mainz was stopped
this morning.

Based on the water level on the upper Rhine, the forecasts assume that High Water Mark II
will be reached till 28th of January 2018.

At the moment, we would suggest a resumption between the 28th- 29th of January 2018.

Our barges are currently at following locations:

KV Triangle                          since this morning in Mainz
MS Monika Deymann        since this morning in Mainz
KV Joline                              left Rotterdam this morning        eta Mainz 29.01.2018
MS Freienstein                    currently in Rotterdam                 eta Mainz 30.01.2018
MS Sophie Deymann          left Rotterdam meanwhile           eta Mainz 29.01.2018
MS Windeck                         currently  in Rotterdam                eta Mainz 30.01.2018

We kindly ask you for your understanding, that we have to fully reject all kind of costs that will arise due to the high Water situation.

Our members from the customer service team will provide you with further information.

Frankenbach Container Service GmbH

19 Dec Customer Information 12/2017

Dear customers,

we would like to inform you regarding the following current issues:

 

  • Bunker Adjustment Factor for Barge transports in January 2018
  • Terminal Opening Hours during the upcoming working holidays
  • Thank you!

 

Bunker Adjustment Factor for Barge Transport in January 2018

The gasoil-price-index monitored by CBRB, Rotterdam, has risen slightly. Hence, Bunker Adjustment Factor (BAF) for January 2018 is settled to scale 17 of the Frankenbach BAF Scheme. Kindly take note.

You may find the complete Frankenbach BAF Scheme in the download area of our homepage www.frankenbach.com

 

Terminal Opening Hours during the upcoming holidays

Please consider the upcoming holidays on 25th and 26th December and the 01st  January 2018 and the resulting shortened working weeks (calendar week 52 and 01) for your transport planning. The FCT container terminal and the office in Mainz will be closed.

Furthermore, there will be limited arrivals and exits in our train transport in this period of time.
Please kindly consider these restrictions in your transport planning. We therefore ask for early reservations.
Please contact our team planning in case of any further questions.

 

Thank you!

In sincere appreciation of the spirit of cooperation that we share, management and staff of Frankenbach Container Service GmbH and Frankenbach Container Terminals GmbH would like to wish you a peaceful holiday season and a successful New Year.

 

Frankenbach Container Service GmbH

23 Nov Customer Information 11/2017

Dear customers,

we would like to inform you regarding the following current issues:

  • Bunker Adjustment Factor for Barge transports in December 2017
  • Expansion of our Reeferservice

Bunker Adjustment Factor for Barge Transport in December 2017

The gasoil-price-index monitored by CBRB, Rotterdam, has risen slightly. Hence, Bunker Adjustment Factor (BAF) for December 2017 is settled to scale 16 of the Frankenbach BAF Scheme. Kindly take note.

You may find the complete Frankenbach BAF Scheme in the download area of our homepage www.frankenbach.com

Expansion of our Reeferservice

In order to meet the increasing demand of our customers for a chilled transport chain, we are constantly working on further expansion in this field.

This means for our interested customers that we as of now offer reefer repairs by a specifically trained reefer mechanic.

This complements our service in this area optimally: we are already equipped with the appropriate connections on our chassis, barges and at the terminal so that a continuous cooling chain can be ensured.

Please contact us for further information.

Frankenbach Container Service GmbH

19 Jul Low Water Scale 1 and Low Water Scale 2

Dear customers,

kindly note following information:

  • Low Water Scale 1
  • Low Water Scale 2

Sunday morning, July 16, 2017 at 05:00 a.m. the scale in Kaub showed a water level of 148 cm. For shipments from this effective date on Low Water Surcharge (KWZ) scale 1 as per Frankenbach Low Water Scale will became applicable.

Sunday morning, July 19, 2017 at 05:00 a.m. the scale in Kaub showed a water level of 126 cm. For shipments from this effective date on Low Water Surcharge (KWZ) scale 2 as per Frankenbach Low Water Scale will became applicable.

 

Low Water Scale

 

We shall keep you advised about the development. For further information you may also consult our homepage www.frankenbach.com.

Frankenbach Container Service GmbH

12 Jul Low Water Scale suspended

Dear valued customers,

Wednesday morning, July 12th, 2017 a t 05:00 a.m. the water level Pegel Kaub reached 158 cm. Therefore we are going to suspend the Low Water Surcharge for all departures as of at 12th.

We are going to keep you updated. For further information you may also consult our homepage www.frankenbach.com.

Frankenbach Container Service GmbH

10 Jul Low Water Scale 1

Dear customers,

kindly note following information:

  • Low Water Scale 1

 

Sunday morning, 09.07.2017 at 05:00 a.m. the scale in Kaub showed a water level of 145 cm. For shipments from this effective date on Low Water Surcharge (KWZ) scale 1 as per Frankenbach Low Water Scale will became applicable.

 

Low Water Scale

 

We shall keep you advised about the development. For further information you may also consult our homepage www.frankenbach.com.

Frankenbach Container Service GmbH